Client: Airtricity

Cost: Confidential

Completion Date: Currently on site under construction

Description: 16kM cable route alignment design from the wind farm site to the substation at Clonkeen Co. Kerry. The design includes for road and river crossings, peat excavation, rock removal, floating trench construction, routing through forestry, national primary road crossing (thrust boring under the roadway) and statutory processes associated with the proposals. The brief includes site supervision of the construction works.

 

 