The Kilo Scale Facility consisted of a single storey extension to an existing production building on
the GSK Pharmaceutical site at Currabinny, Carrigaline, Co. Cork. The project was a carried out under
three separate contracts to meet the clients construction timeline requirements. The construction
commenced in April 2015 and was completed in January 2016. The overall project budget was €9.4M,
the Civil/Structural element of which was €1.5M.
Malachy Walsh & Partners were the lead Civil/Structural Consultants on the Project, while DPS
Engineering were the lead Electrical, Mechanical & Process Consultants on the project. Overall, there
was 60,000 man hours worked on the project which equated to an average of 35 people worked on the
project per day. However, there were periods during the construction where construction went to 24
hours per day to meet the schedule deadlines. The project experienced no RIIR, no lost time and only
4no. first aid incidents.
Construction Complete